Life of Mine Extension Feasibility Study of Mponeng Mine

13 April 2021
AngloGold Ashanti’s Mponeng mine is located in South Africa’s Gauteng province. After the successful completion of the Pre-Feasibility study for mining below the 120 Level, the feasibility phase commenced establishing if the current hoisting capacity will be sufficient for personnel, material, slinging, and rock logistics during daily operations as well as for project-related logistics. The main objective of the simulation was to analyse how the proposed project infrastructure would tie into existing operations.
Life of Mine Extension Feasibility Study of Mponeng Mine

Approach

The model considered the interactions and real-world dynamic nature of:

  • Shafts Logistics
  • Rock Hoisting
  • Level Haulage and equipment
  • Personnel
  • Project ramp material handling systems

These interactions were analysed to increase the shift utilisation and increase the hoisting capacity for material, by changing from a three-shift system to a two-shift system.

shift comparison mine feasibility study 1024x362
Shift Comparison

Results

The model simulated the complete LOM to establish if the proposed two-shift system will be sufficient to achieve the required annual target tonnages. The following graphs display whether the current hoisting capacity will be adequate to facilitate the transportation of personnel, rock, material, and slinging to reach the annual target.

personnel requirements mine feasibility study 768x321
Personnel requirements

For personnel logistics, the hoisting capacity was exceeded during the peak production periods.

material car requirements mine feasibility study 1024x484
Material Car Requirements

Two shift schedule indicated sufficient capacity to hoist material cars.

sling trips per week mine feasibility study
Sling trips per week

Slinging did exceed the scheduled capacity during one period, but the spare capacity from the material allowed for sufficient capacity.

The study established that the proposed two-shift schedule with the current hoisting capacity will not be able to support the Hoisting operations to achieve the required production target.

lom hoisting capacity mine feasibility study
LOM Hoisting Capacity (annual tonnage)

Following these results, the client rescheduled the production profile to meet the hoisting capacity specified. The restated production profile is shown below.

restated production profile mine feasibility study
Restated production profile

If you are looking for accurate decision-making support, contact us today to speak to one of our experts.

Contact us

T: +27126402600    
E: This email address is being protected from spambots. You need JavaScript enabled to view it.